14 Nov Bayan Lepas LRT construction to start in Q4 2023: Zairil
Published by The Vibes • 21/10/2022
Zairil Khir Johari says the qualified entities will be given four months to prepare their requests for proposal for submission, with evaluation of the proposals expected to take three months, after which a report will be prepared for the tender and procurement committees to make the final decision. – Bernama pic, October 21, 2022
GEORGE TOWN – Penang expects the Bayan Lepas Light Rail Transit (LRT) project construction to begin in the fourth quarter of next year, subject to the federal authorities’ approval of the last segment of the LRT line involving the location of the LRT depot on the reclaimed Penang South Islands.
State Infrastructure and Transport Committee chairman Zairil Khir Johari said the prequalification registration exercise for the LRT project, conducted from July 25 to August 19, saw 45 companies registering interest and purchasing the prequalification documents.
The prequalification exercise was to identify and pre-qualify suitable contractors to participate in the request for proposal (RFP) tender process for the engineering, procurement, construction, testing, and commissioning of the LRT’s viaducts, stations, depot, system, and other associated works, as well as the funding, operation, and maintenance of the LRT system.
“By the end of the submission deadline on October 7, 2022, we received eight submissions from local and international consortiums. Evaluation of the submissions is currently being carried out by the technical and financial committees.
“A report will be prepared and presented to the tender committee followed by the procurement committee. The committees will identify the qualified entities to be formally invited to participate in the RFP exercise and the RFP tender is expected to open in early 2023,” he said in a statement here today.
According to him, the qualified entities will be given four months to prepare their RFP proposals for submission. Thereafter, evaluation of the proposals is expected to take three months, after which a report will be prepared for the tender and procurement committees to make the final decision.
The LRT is one of the main components of the Penang Transport Master Plan and it is part of a long-term strategy to overcome the problem of traffic congestion in the state.
The Penang government aims to start construction of the LRT line that connects Komtar and Bayan Lepas next year. – Bernama, October 21, 2022
No Comments